Mundial engineering 90 day plan
Mundial engineering · 90 day plan
May 1 to Jul 31, 2026 · today is May 11
On track
At risk
Blocked
Planned
Hard deadline
MAY
JUNE
JULY
TODAY
CARTER ENDS
JOAQUIN ENDS
CORE IP · CADMUS
Cadmus 4.0
Tony, Adrian → Carter, Joaquin
requirements
build · blocked until reqs done
at risk · reqs TBD
INTERNAL TOOLING
Thunderstorm
Adrian · launched April 2026
operational · serves political customer · iterate for new verticals
iterate v2
Pub Dev Dashboard
Adrian · launched May 1, 2026
✓ launched
customer rollout · retire pub.mundialmedia.com
reports.mundialmedia.com
launched · rolling out
Ops Console
Carter, Joaquin
v1 · rebuild Jeff's tool
v1.5 · merge Alex's Pub Dev
operations.mundialmedia.com
v1 in build
Mundial Intelligence
Ramon, Alejandra
Screaming Frog
data science
intelligence.mundialmedia.com
on track
DATA PARTNERSHIPS
Boostr integration
Owner TBD · external vendor (Boostr)
vendor delivery window
blocked · slipped past May 6
OPEN ITEMS · DECISIONS NEEDED
Cadmus 4.0 requirements lock
Tony + Adrian define high-level requirements (Alejandra supports).
Build cannot start until this is done. Target before June 1.
Post Jul 20: zero dev capacity
VP Eng search planned for Q4. Decide what survives
the consultant exits.
Boostr · vendor delivery unconfirmed
Pub Dev cutover · retire pub.mundialmedia.com Jun–Jul